header.skiplinktext header.skiplinkmenu
Cambiar país
  • Buscar país

    País seleccionado

    Resultados

    Todos los países

    Boutique en línea

    • ÖSTERREICH / €
    • ANDORRA / €
    • AUSTRALIA / a$
    • BELGIUM / €
    • Brazil / €
    • CANADA / CAD
    • CHINA / CN¥
    • CROATIA / €
    • CYPRUS  / €
    • CZECH REPUBLIC / €
    • DENMARK / kr
    • ESTONIA / €
    • FINLAND / €
    • FRANCE / €
    • GERMANY / €
    • GREECE / €
    • HONG KONG SAR, CHINA / hk$
    • HUNGARY / €
    • ICELAND / KR
    • IRELAND / €
    • ITALY / €
    • JAPAN / ¥
    • KOREA / KRW
    • LATVIA / €
    • LITHUANIA / €
    • LUXEMBURG / €
    • MACAU SAR, CHINA / MOP
    • MALAYSIA / MYR
    • MEXICO / €
    • NETHERLANDS / €
    • NORWAY / NOK
    • POLAND / €
    • PORTUGAL / €
    • REST OF THE WORLD
    • ROMANIA / €
    • RUSSIA  / ₽
    • SINGAPORE / SGD
    • SLOVAKIA / €
    • SLOVENIA / €
    • SPAIN / €
    • SWEDEN / SEK
    • SWITZERLAND / CHF
    • TAIWAN, CHINA / NT$
    • THAILAND / THB
    • TURKEY / TRY
    • UAE / AED
    • UNITED KINGDOM / £
    • UKRAINE  / UAH
    • USA / $

    iwc-ppc-language-
    Shopping Bag
    CONEXIÓN A IWC

    THE MANUFACTURING CENTRE TIME LAPSE

    The official laying of the foundation stone in June 2016 marked the kickoff not only for the major structural work of IWC’s new manufacturing center, but also for the largest investment that IWC has ever undertaken. The building with a total floor area of 13,500 square meters presents an opportunity to bring together production areas that were previously spread out across different locations and thus to further optimize the existing production process workflows and structures. Once construction is complete, the site will provide workspace for around 400 skilled employees. The official opening ceremony is scheduled for June 2018. Take a look at the process of the construction work since its beginning by clicking on the video.

    The official laying of the foundation stone in June 2016 marked the kickoff not only for the major structural work of IWC’s new manufacturing center, but also for the largest investment that IWC has ever undertaken. The building with a total floor area of 13,500 square meters presents an opportunity to bring together production areas that were previously spread out across different locations and thus to further optimize the existing production process workflows and structures. Once construction is complete, the site will provide workspace for around 400 skilled employees. The official opening ceremony is scheduled for June 2018. Take a look at the process of the construction work since its beginning by clicking on the video. 

    Construction Timeline

    June 2016 Official laying of the foundation stone/concrete casting of the foundation stone box.
    4 May 2017 Topping out ceremony/completion of the major structural work
    October 2017 Relocation commences – all departments from Neuhausen (case production, surface machining, case assembly, production of parts for movements)
    January 2018 Movement assembly departments relocate from Schaffhausen to Merishausen
    June 2018 Official opening ceremony and open day – one of the highlights of IWC’s 150th anniversary year
    Total Construction Time 21 months